Waldo Middle School Winter Bond Construction Update! | Información actualizada de los trabajos del proyecto del bono de construcción del invierno de la Escuela Intermedia Waldo

Construction at Waldo began in the fall and has steadily continued into the school year. The bond-funded construction includes a classroom addition with four new general classrooms and four new science labs. Work also includes a cafeteria expansion, a new multipurpose fitness room and removal of all portable classrooms.

Construction at Waldo has made a lot of progress! Construction crews poured foundational concrete slabs for the classroom addition and multipurpose fitness room after completing plumbing work. They are now framing the classroom addition and multipurpose fitness room.

The existing auxiliary gym, new multipurpose fitness room and classroom addition will all be connected to the existing building as demonstrated in the first image below.

Site plan classroom addition and multipurpose fitness room

The classroom addition is highlighted orange, and the multipurpose fitness room is highlighted blue.

Classroom addition

Classroom addition: foundational concrete slab + wall framing

Multipurpose fitness room

Classroom addition + multipurpose fitness room

Construction crews demolished the cafeteria wall, excavated the site and leveled the ground to prepare for construction of the cafeteria expansion. The foundational concrete slab has been poured.

Cafeteria expansion

The cafeteria expansion will be built on this concrete slab.

Over $14.3 million will be invested in improvements at Waldo! Work is expected to be complete by early fall of 2020.

Thank you for your continued patience and understanding. The improvements at Waldo will help relieve overcrowding, expand learning opportunities for science education and better support students as they prepare for the next steps in their education.

You can track Waldo’s construction project by viewing their photo gallery on the bond page. A photo album can also be found on Facebook, and more information about bond projects can be found on the district website.

Bond elements w/ text

 

Las labores de construcción en Waldo iniciaron en el otoño y continúan de forma constante durante el año escolar. La construcción financiada por el bono comprende la incorporación de un área con cuatro aulas nuevas de educación general, además de cuatro laboratorios nuevos de ciencias. A su vez, las labores incluyen la ampliación de la cafetería, un gimnasio multifuncional y la eliminación de todas las aulas portátiles.

Las labores de construcción en Waldo han avanzado mucho. Después de haber finalizado los trabajos de plomería, el personal de la construcción vertió las placas de concreto de la cimentación de las nuevas aulas y del gimnasio multifuncional. Actualmente instalan la estructura de las nuevas aulas y del gimnasio multifuncional.

El actual gimnasio auxiliar, el nuevo gimnasio multifuncional y las nuevas aulas incorporadas estarán todas conectadas al plantel existente como lo muestra la primera imagen a continuación.

Site plan classroom addition and multipurpose fitness room

La incorporación de las nuevas aulas se destaca en color naranja, y el gimnasio multifuncional se destaca en color azul.

Classroom addition

Nuevas aulas: cimentación de placas de concreto + estructura

Multipurpose fitness room

Nuevas aulas + gimnasio multifuncional

El personal de la construcción derribó el muro de la cafetería, excavó la tierra y niveló la superficie para preparar el terreno para la ampliación de la cafetería. Se ha vertido la losa de hormigón fundacional.

Cafeteria expansion

Ampliacion de la cafeteria

¡Más de $14.3 millones serán invertidos en mejoras en Waldo! Está previsto que las labores de construcción finalicen a principios del otoño del 2020.

Gracias por su permanente paciencia y comprensión. Las mejoras en Waldo ayudarán a reducir el hacinamiento, al aumento de las oportunidades de aprendizaje en la educación científica y para apoyar mejor a los estudiantes durante el tiempo que se preparan para los siguientes pasos de su educación.

Puedes ver y consultar el proyecto de construcción en photo gallery en la página del proyecto del bono. Se encuentra un álbum de fotografías en Facebook, y puedes obtener más información sobre los proyectos de construcción en el district website.

Bond elements

2020-02-11T12:12:32-08:00January 27th, 2020|

VIDEO: Students Help Explain the Bond Project at Waldo Middle School | VÍDEO: Los estudiantes ayudan a explicar el proyecto de bonos en la escuela intermedia Waldo

Waldo Middle School is one of four schools currently under construction thanks to the bond that was passed by Salem and Keizer voters in 2018. Two students help explain the construction project happening at Waldo. See how the improvements are going to benefit the school, their classmates and the entire Waldo community.

La escuela intermedia Waldo es una de las cuatro escuelas actualmente en construcción gracias al bono que fue aprobado por los votantes de Salem y Keizer en 2018. Dos estudiantes ayudan a explicar el proyecto de construcción que está ocurriendo en Waldo. Vea cómo las mejoras beneficiarán a la escuela, a sus compañeros de clase y a toda la comunidad de Waldo.

(Para subtítulos en español, haga clic en el botón de configuración en el video, luego haga clic en “Subtítulos / CC” y seleccione Español.)

 

2020-01-06T15:53:48-08:00December 27th, 2019|

Temporary Traffic Adjustments at Waldo Middle School | Ajustes temporales al tránsito vehicular en la Escuela Intermedia Waldo

Temporary Traffic Adjustments at Waldo Middle School

Bond construction has begun at Waldo! For safety reasons, we need to make some temporary changes to traffic flow for student pick-up and drop-off.

Traffic flow changes will be in effect from Oct. 28 until just after Thanksgiving.

Please refer to the map below for traffic flow adjustments.

Traffic flow changes

Traffic flow adjustment map

Thank you for your patience and understanding! We are excited about the amazing improvements planned for Waldo!

For more information about the 2018 Bond Program, please visit the district website.

 

Ajustes temporales al tránsito vehicular en la Escuela Intermedia Waldo

¡En Waldo, ha comenzado la construcción del proyecto de bonos! Por razones de seguridad, necesitamos hacer algunos cambios temporales al tránsito vehicular en el área de acceso designada para dejar y recoger a los estudiantes.

Los cambios al tráfico vehicular entrarán en efecto a partir del 28 de octubre hasta justo después del Día de Acción de Gracias.

Por favor, consulte el siguiente mapa con los ajustes del tránsito vehicular.

Traffic flow map Spanish

Mapa con los ajustes del tránsito vehicular

¡Le agradecemos su paciencia y comprensión! ¡Estamos entusiasmados por las maravillosas mejoras previstas para Waldo!

Para información adicional sobre el programa de bonos de 2018, por favor visite el sitio web del distrito.

2019-10-25T10:32:08-08:00October 25th, 2019|

Construction Continues at Waldo! | ¡La construcción continua en Waldo!

Construction Continues at Waldo!

Waldo broke ground this summer to kick off its bond-funded construction project, and we are excited for the improvements planned for our school!

Construction began in the fall in select areas inside the building and will be ramping up soon with work outside on the new classroom addition and multipurpose fitness room. The new addition will include four new general education classrooms and four new science labs. Work also includes the removal of all portable classrooms. More construction activity is planned to start as the school year continues.

Adjustments have been made to our daily operations and are continually being evaluated to ensure the safety of our students during construction. Work on the cafeteria expansion has begun, and tables have been set up in the gym for students to eat their lunches while the cafeteria space is under construction.

Bond construction at Waldo 2019

Students eating lunch in the gym due to bond funded construction

Bond construction at Waldo 2019

Students eating lunch in the gym due to bond funded construction

Over $14.3 million will be invested in improvements at Waldo! Work is expected to be complete in August 2020.

Thank you for supporting our students and for your continued understanding and patience. The bond-funded improvements will benefit the Waldo community and enhance our ability to support student achievement.

You can check on Waldo’s photo gallery to track the progress of construction! Photos will be added to the gallery as construction activities pick up and changes occur on site. A photo album for Waldo will also be added to the district’s Facebook page.

For construction photos, project lists and more information on construction at Waldo, please visit the district website.

 

¡La construcción continua en Waldo!

¡Waldo comenzó este verano su proyecto de construcción financiado por los fondos del bono, y estamos entusiasmados con las mejoras planificadas para nuestra escuela!

La construcción comenzó en el otoño en áreas seleccionadas dentro de la escuela y pronto se comenzará a trabajar fuera de la escuela con la adición de un salón de clases nuevo y un gimnasio de usos múltiples. La nueva adición incluirá cuatro salones de clases de educación general nuevos y cuatro laboratorios de ciencias nuevos. El trabajo de construcción también incluye la remoción de todos los salones de clases portátiles. Se ha planificado comenzar más actividades de construcción a medida que el año escolar continúe.

Se han realizado ajustes en nuestras operaciones diarias y se evalúan continuamente para garantizar la seguridad de nuestros estudiantes durante la construcción. El trabajo en la expansión de la cafetería ha comenzado, y se han establecido mesas en el gimnasio para que los estudiantes coman sus almuerzos mientras el espacio de la cafetería está en construcción.

Bond construction at Waldo 2019

Estudiantes almorzando en el gimnasio durante la construcción

Bond construction at Waldo 2019

Estudiantes almorzando en el gimnasio durante la construcción

¡Se invertirán más de 14,3 millones de dólares en las mejoras para la escuela Waldo! Se espera que el trabajo de construcción finalice en agosto del 2020.

Gracias por apoyar a nuestros estudiantes y por su continua comprensión y paciencia. Las mejoras financiadas por los fondos del bono beneficiarán a la comunidad de Waldo y mejorarán nuestra capacidad de apoyar el rendimiento estudiantil.

¡Puede ingresar a la galería de fotografías de Waldo para darle seguimiento al progreso de la construcción! Se agregarán fotos a la galería a medida que se realicen las actividades de construcción y se produzcan cambios en el sitio. Se adicionará un álbum fotográfico para la escuela Waldo en la página de Facebook del distrito.

Para ver las fotografías de la construcción, las listas del proyecto y más información acerca de la construcción en Waldo, por favor ingrese en la página web del distrito.

2019-10-25T08:14:15-08:00October 25th, 2019|

VIDEO: Waldo Middle School Bond Projects Overview | VÍDEO: Descripción general de los proyectos de bonos de la escuela intermedia de Waldo

Here is an overview of the bond construction projects happening at Waldo!

¡Aquí hay una descripción general de los proyectos de construcción de bonos que están sucediendo en Waldo!

2019-09-19T13:39:24-08:00September 19th, 2019|

North Salem High School Marching Band Activities at Waldo Middle School this Summer | Este verano se llevarán a cabo las actividades de la banda musical de marcha de la Escuela Preparatoria North Salem en la Escuela Intermedia Waldo

North Salem High School Marching Band Activities at Waldo Middle School this Summer

North Salem High School’s campus is closed for the summer due to bond-funded construction. As a result, North Salem High School’s band camp will be held at Waldo Middle School from July 31 through August 23. Band activities are scheduled at Waldo from 8 a.m. until 5 p.m. Exceptions to this schedule are on August 15, 20 and 21, when practice will instead be held from 1 p.m. to 8 p.m.

As a neighbor of Waldo, here are some things you may see or hear during this time:

• Great music!
• The band director giving students instruction over the loudspeaker
• Drum line
• Color guard

Please share this information with your neighbors. If you have any questions about North Salem High School band activities, please contact the North Salem High School Office at (503) 399-3241.

For more information about the 2018 bond program, visit the bond projects page on the district website.


Este verano se llevarán a cabo las actividades de la banda musical de marcha de la Escuela Preparatoria North Salem en la Escuela Intermedia Waldo

Las instalaciones escolares de la Escuela Preparatoria North Salem están cerradas durante el verano debido a las construcciones financiadas por los fondos del bono. Debido a esto, el campamento de la banda musical de la Escuela Preparatoria North Salem se llevará a cabo en la Escuela Intermedia Waldo desde el 31 de julio hasta el 23 de agosto. Se han programado las actividades de la banda en la escuela Waldo desde las 8 a.m. hasta las 5 p.m. Las excepciones a esta programación serán los días 15, 20 y 21 de agosto, cuando las prácticas se llevarán a cabo desde la 1 p.m. hasta las 8 p.m.

Como vecino de la escuela Waldo, les presentamos a continuación algunas de las actividades que usted podrá ver o escuchar durante este período de tiempo:

• ¡Buena música!
• El director de la banda dándole instrucciones a los estudiantes a través del altoparlante
• Formaciones de tambores
• Coreografías con banderas

Por favor, comparta esta información con sus vecinos. Si usted desea formular alguna pregunta referente a las actividades de la banda musical de la Escuela Preparatoria North Salem, por favor, contacte con la oficina escolar de North Salem al (503) 399-3241.

Para obtener más información sobre el programa de los fondos del bono, ingrese al enlace del proyecto de los fondos del bono en la página web del distrito.